Construction cash flow: build a 13-week forecast for your building business

Construction cash flow: build a 13-week forecast for your building business

By Smart Way Builds · Updated

A profitable building job can still leave you short of cash. Materials and subcontractors may need payment before a customer's progress payment arrives. Construction cash-flow planning makes that timing visible before it becomes a supplier call you cannot answer.

A practical starting point is a rolling 13-week forecast. It is a planning worksheet, not an accounting cash-flow statement or a promise about when customers will pay. Update it weekly and keep a separate view of job profit.

What belongs in a construction cash-flow forecast?

Start with available business cash, then list expected receipts and payments by the week cash will actually move. Do not use the invoice issue date as a substitute for a realistic receipt date.

  • Customer receipts: expected progress payments and other collections.
  • Job payments: materials, subcontractors, direct wages, equipment hire and deposits.
  • Business payments: office costs, insurance, loan repayments and other overheads.
  • Tax and payroll obligations: amounts and dates checked with your accountant.
  • Financing and owner movements: shown separately rather than called job revenue.

Use GST-inclusive cash movements where GST is actually paid or received, and separately plan tax settlements. This differs from a GST-exclusive job-margin comparison. Do not assume collected GST is all available to spend; your accounting method and credit eligibility matter.

A worked four-week extract

Fictional business-wide AUD cash amounts, including any GST within the listed receipts and payments. These are not construction prices or a product-generated forecast. Tax settlements are assumed outside this four-week extract and must be added when due.

WeekOpening cashReceiptsPaymentsClosing cash
1$30,000$20,000$25,000$25,000
2$25,000$0$18,000$7,000
3$7,000$35,000$22,000$20,000
4$20,000$15,000$17,000$18,000

Closing cash = opening cash + receipts − payments. Carry each week's closing balance into the next opening balance. Week 2 is the lowest point here, even though the four-week total finishes positive.

Stress-test a late progress payment

If the $35,000 receipt moves from week 3 to week 4, week 3 closes at negative $15,000: $7,000 − $22,000. Week 4 still finishes at $18,000 after the delayed receipt, but that does not solve the earlier shortage. A positive month-end balance can hide a mid-month problem.

Mark uncertain receipts, test realistic delays and decide what to do before the low point: clarify claim evidence, follow up collections, review discretionary purchases or discuss suitable finance. Do not assume you can delay agreed supplier payments without consequences.

Keep the forecast useful each week

  1. Replace the finished week's estimates with actual cash movements.
  2. Update receipt dates using current customer information.
  3. Add approved unpaid invoices and known upcoming purchases.
  4. Check wages, overheads and tax dates across the business, not just one job.
  5. Add another week at the end and record why assumptions changed.

Use job budgets and invoice records as inputs, not as a complete cash forecast. Smart Way Builds distinguishes approved costs from paid records; a future receipt date and remaining-cost assumption still need your review.